| + | ====== No municipal water connection after possession? Pick your route by where the file is stuck ====== | ||
| + | |||
| + | |||
| + | <WRAP center round info 95%> | ||
| + | **Quick Reply:** Tanker water after possession? Use RERA if the builder never applied, or citizen charter and service guarantee timelines if the water board holds the file. | ||
| + | </ | ||
| + | |||
| + | **Reviewed on:** 2026-06-12. | ||
| + | |||
| + | {{: | ||
| + | |||
| + | Your remedy depends on one fact: who is holding the file. If the builder never applied to the water board, your dispute is with the builder, and RERA is your forum. If the builder applied and the municipal water board is sitting on the application, | ||
| + | |||
| + | ===== Branch 1: the builder never applied ===== | ||
| + | |||
| + | Check your cost sheet. Most builders collect "water and sewerage connection charges" | ||
| + | |||
| + | Water supply is part of the development the promoter promised in the sanctioned plan, and providing it is a duty under section 11(4) of the RERA Act, 2016. Send the builder a dated letter demanding, within 15 days, proof of the application to the water board, the receipt for connection charges paid to the board, and a committed date. If that produces nothing, file before your state RERA (portals linked from [[https:// | ||
| + | |||
| + | ===== Branch 2: the application is stuck with the water board ===== | ||
| + | |||
| + | Municipal water boards and corporations run a defined process: application with the sanctioned plan and OC, payment of connection and road-cut charges, site inspection, then meter fixing. Each major board publishes a citizen charter with a timeline for a new connection. Delhi Jal Board, BWSSB in Bengaluru and the Hyderabad water board all commit to fixed working-day limits, and in many states the new water connection is a notified service under a public services guarantee law: the Madhya Pradesh Lok Sewa Guarantee Adhiniyam 2010, Karnataka' | ||
| + | |||
| + | So the sequence is: written status request to the dealing engineer quoting the application number, then the citizen charter timeline, then the service guarantee appeal where your state has one, then the municipal grievance cell or commissioner. In parallel, the water board is a public authority, so an RTI fetches the truth about the file: | ||
| + | |||
| + | < | ||
| + | To: The Public Information Officer, [Water Board / Municipal Corporation, | ||
| + | Water Supply Department] | ||
| + | |||
| + | Re: Application no. [X] dated [date] for new water connection, | ||
| + | [building name, address] | ||
| + | |||
| + | Under the RTI Act, 2005, kindly provide: | ||
| + | 1. The current status of the above application and the officer with | ||
| + | whom the file is pending. | ||
| + | 2. Certified copy of the file noting sheet from receipt till date. | ||
| + | 3. The inspection report, if any, and the list of objections raised. | ||
| + | 4. The timeline notified in your citizen charter or under the state | ||
| + | | ||
| + | has been crossed in this case. | ||
| + | </ | ||
| + | |||
| + | A noting sheet that shows the file parked on one desk for six weeks does your arguing for you. Filing basics are at [[file-rti-online-india|how to file RTI online]], and your state' | ||
| + | |||
| + | ===== Branch 3: tanker water, billed to you ===== | ||
| + | |||
| + | Do the arithmetic before the next maintenance bill. A 6,000-litre private tanker costs roughly Rs 900 to Rs 1,500 depending on the city and season. A 100-flat society using a modest 60,000 litres a day needs about 10 tankers daily, which is Rs 3 lakh to Rs 4.5 lakh a month, recovered from residents through maintenance. Metered municipal supply for the same volume costs a small fraction of that. Every month of delay is a transfer from your pocket. | ||
| + | |||
| + | Demand the tanker invoices and the maintenance account head-wise. If the builder controls maintenance and will not show the accounts, that is its own dispute, covered in [[practical-guides: | ||
| + | |||
| + | ===== Branch 4: connection exists, but in the builder' | ||
| + | |||
| + | Common in projects where the builder took a bulk or construction-period connection. The permanent arrangement is a transfer to the society or association once it is formed, along with the other common services. If no society exists yet, that is the prior problem; see [[practical-guides: | ||
| + | |||
| + | ===== What this guide does not cover ===== | ||
| + | |||
| + | Electricity follows a different statute, the Electricity Act, 2003, with its own DISCOM timelines and an ombudsman; that route is in the companion guide on [[practical-guides: | ||
| + | |||
| + | ===== FAQs ===== | ||
| + | |||
| + | ==== The builder says the water board is "not giving connections in this area". What do I check? ==== | ||
| + | |||
| + | Ask the board in writing, or by RTI, whether the project area is within its supply network and whether any application from the builder exists. Builders sometimes blame the board to mask the fact that connection charges were never paid. The board' | ||
| + | |||
| + | ==== Is there a fixed national timeline for a new water connection? ==== | ||
| + | |||
| + | No. Water is a municipal and state subject. The binding timeline is in your board' | ||
| + | |||
| + | ==== Can RERA order the water board to give the connection? ==== | ||
| + | |||
| + | No. RERA binds the promoter, not the municipal board. RERA directs the builder to complete his side, pay the charges and pursue the connection, and can award compensation. Pressure on the board itself travels through the charter, the service guarantee appeal and the municipal grievance route. | ||
| + | |||
| + | ==== We paid water connection charges in the cost sheet. Can we get them back? ==== | ||
| + | |||
| + | If the builder never paid them to the board, claim a refund or proper accounting before RERA or the consumer commission through [[https:// | ||
| + | |||
| + | ==== Does an occupancy certificate guarantee water supply exists? ==== | ||
| + | |||
| + | An OC is normally granted only when water supply and sanitation arrangements per the sanctioned plan are in place. A project with an OC but no working supply suggests either a part-OC situation or supply shown on paper through borewells and tanks. Get the OC copy and check what it actually covers. | ||
| + | |||
| + | ==== Who applies for the connection, the builder, me, or the society? ==== | ||
| + | |||
| + | For the building-level or bulk connection, the builder before handover and the society after it. Individual flat-level connections exist in some cities for plotted or low-rise formats. The board' | ||
| + | |||
| + | ===== Related guides ===== | ||
| + | |||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[file-rti-online-india|How to file RTI online]] | ||
| + | |||