Differences
This shows you the differences between two versions of the page.
| — | practical-guides:builder-delayed-electricity-connection-possession [2026/07/22 17:47] (current) – created - external edit 127.0.0.1 | ||
|---|---|---|---|
| Line 1: | Line 1: | ||
| + | {{htmlmetatags> | ||
| + | |||
| + | ====== Moved in, but still no permanent electricity connection? Do these five things first ====== | ||
| + | |||
| + | |||
| + | <WRAP center round info 95%> | ||
| + | **Quick Reply:** Flat on builder DG power after possession? Electricity Act section 43, DISCOM connection timelines, CGRF and ombudsman route, plus the RERA angle. | ||
| + | </ | ||
| + | |||
| + | **Reviewed on:** 2026-06-12. | ||
| + | |||
| + | {{: | ||
| + | |||
| + | You took possession months ago, yet your flat runs on the builder' | ||
| + | |||
| + | - Check the per-unit rate on the builder' | ||
| + | - Ask the builder in writing for the permanent connection application number, the date it was filed with the DISCOM, and the status of the electrical inspector' | ||
| + | - Ask the DISCOM' | ||
| + | - Find out what is pending: the builder' | ||
| + | - Open a dated paper trail. Every later forum, from the consumer grievance forum to RERA, runs on it. | ||
| + | |||
| + | ===== The law on supply timelines ===== | ||
| + | |||
| + | Section 43 of the Electricity Act, 2003 requires the distribution licensee to give supply within one month of receiving a complete application, | ||
| + | |||
| + | These timelines bind the DISCOM, not the builder. So the first real question in your case is where the file is actually stuck. | ||
| + | |||
| + | ===== Builder' | ||
| + | |||
| + | Before the DISCOM can energise individual meters in a new building, the builder normally has to finish the internal electrification, | ||
| + | |||
| + | The written answers you collected in the five first actions tell you which branch you are on. Often it is both, and you run both tracks in parallel. | ||
| + | |||
| + | ===== The diesel-generator tariff trap ===== | ||
| + | |||
| + | Here is why some builders are slow on purpose. Suppose the DISCOM domestic tariff in your city averages Rs 7 per unit and the builder bills DG or temporary-connection power at Rs 18 per unit. A family using 300 units a month pays Rs 5,400 instead of Rs 2,100, a difference of Rs 3,300 every month. Across a 200-flat project, that is about Rs 6.6 lakh a month flowing through the builder' | ||
| + | |||
| + | ===== Escalation against the DISCOM: CGRF, then ombudsman ===== | ||
| + | |||
| + | If the builder' | ||
| + | |||
| + | - Register a complaint with the DISCOM' | ||
| + | - If unresolved within the SOP timeline, file before the Consumer Grievance Redressal Forum (CGRF) that every DISCOM must run under section 42(5) of the Act. It is free. | ||
| + | - If the CGRF order disappoints or is ignored, appeal to the state Electricity Ombudsman appointed under section 42(6). Also free, and decided on documents in most states. | ||
| + | - Claim the SOP compensation for the missed connection timeline by name. It is rarely paid unless asked for. | ||
| + | |||
| + | ===== The RERA angle against the builder ===== | ||
| + | |||
| + | Electricity supply is part of the development the promoter promised in the sanctioned plan and brochure. Failing to provide permanent connections after offering possession breaches the promoter' | ||
| + | |||
| + | ===== Where RTI fits, and where it does not ===== | ||
| + | |||
| + | State-owned DISCOMs (for example MSEDCL, UPPCL, BESCOM, TANGEDCO) are public authorities under the RTI Act. File an RTI with the DISCOM' | ||
| + | |||
| + | Private DISCOMs such as Tata Power, Adani Electricity, | ||
| + | |||
| + | ===== FAQs ===== | ||
| + | |||
| + | ==== Can I apply for my own meter without the builder' | ||
| + | |||
| + | Many DISCOMs ask for an NOC or possession proof from the developer, but the 2020 Rights of Consumers Rules push licensees towards accepting ownership or occupancy documents. If the DISCOM insists on an NOC the builder will not give, get the refusal in writing from both sides; it makes a clean CGRF and RERA record. | ||
| + | |||
| + | ==== Is the Rs 1,000-a-day penalty under section 43 automatic? ==== | ||
| + | |||
| + | No. It is imposed through the adjudication process, and the SOP compensation under your state' | ||
| + | |||
| + | ==== The builder charges a fixed "power backup" | ||
| + | |||
| + | Only to the extent your agreement and the maintenance terms allow, and the builder must account for actual cost. Demand the diesel bills and the calculation. Unexplained backup charges are a standard head of dispute before state RERA benches and consumer commissions. | ||
| + | |||
| + | ==== Is a temporary connection tariff legally higher? ==== | ||
| + | |||
| + | Yes, DISCOM tariff schedules price temporary supply higher than permanent domestic supply. That is exactly why a building stuck on a temporary connection for months after possession is costing you money every billing cycle, and why the builder' | ||
| + | |||
| + | ==== Can RERA actually order the electricity connection? ==== | ||
| + | |||
| + | RERA can direct the promoter to complete the works and formalities on his side and can award compensation. It cannot direct the DISCOM, which answers to the CGRF, the ombudsman and the regulator. That is why the two tracks run in parallel. | ||
| + | |||
| + | ==== How long does the CGRF take? ==== | ||
| + | |||
| + | State regulations typically require disposal within 45 to 90 days. The ombudsman appeal usually has a similar outer limit. Free, document-driven, | ||
| + | |||
| + | ===== Related guides ===== | ||
| + | |||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[practical-guides: | ||
| + | * [[state-rti-portals-directory|State RTI portal directory]] | ||
| + | |||
| + | Download the permanent electricity connection checklist (PDF). | ||
| + | |||
| + | {{tag> | ||