| - | ===== RTI Application for Toll Collection ===== | + | {{htmlmetatags>metatag-keywords=(RTI toll collection, |
| - | {{like>}} | + | metatag-description=(Toll plaza RTI: get the concession agreement, cost-recovery vs collection, FASTag deduction log, exit-period date. Sample letter, 12 records, real case. 2026.)}} |
| - | {{tag> | + | |
| - | Toll is collected based on a contract, which include the terms and conditions of issuance of Passes to the residents of nearby areas and toll charges fixed for various types of vehicles. Contracts are mostly for a specified period or collection | + | ====== |
| - | There are cases, where the Agreement is for a specified period, but the cost of construction is collected within first one or two years, however, the agency continue to collect same Toll charges from citizens based on erroneous estimation and fixing of Toll Charges by the authorities regulating such Toll Collection. | + | {{ : |
| - | Please prefer an RTI Application before the PIO of the authority granted the Contract and seek information as detailed below: | ||
| - | <WRAP center round box 90%> | + | **Quick answer.** Suspect that a toll plaza is **collecting beyond its sanctioned cost-recovery period**, charging the **wrong fee for your vehicle category**, **double-deducting** your FASTag, or **denying local-resident passes**? Or simply want to see the **concession agreement** under which a private operator runs a public road? File a **free Right to Information application |
| - | To | + | |
| - | The Public Information Officer \\ | + | |
| - | Name of Public Authority \\ | + | |
| - | …............(Full address) \\ | + | |
| - | PIN Code…………. \\ \\ | + | |
| - | Sub: Request | + | |
| - | Sir, \\ \\ | + | |
| - | Please supply me the following information in respect | + | |
| - | **Details | + | |
| - | Toll Naka No. …………………...(if any)\\ | + | |
| - | Name of Toll Naka……………….\\ | + | |
| - | Road Location | + | |
| - | Name of agency collecting Toll charges…….\\ \\ | + | |
| - | ** Particulars of information required | + | |
| - | [1] certified copy of the Contract Agreement between NHAI and M/s ..............(agency managing the Toll Naka) for collection of Toll at Toll Naka erected at ..........................(give full address of the Toll Naka) | + | |
| - | [2] Certified copy of the document indicating the calculations or estimation or assessment, on the basis of which the Toll Charges for various types of vehicles were fixed for collection | + | ===== The toll-collection |
| - | [3] Amount | + | <WRAP round info 100%> |
| + | **The infographic.** Every toll plaza in India is governed by a **stack | ||
| + | </ | ||
| - | [4] Amount of Toll estimated and required to be collected by M/s .............. from above mentioned | + | ^ Layer ^ Authority ^ Documents that exist ^ |
| + | | **1. Road / project law** | NH Act, 1956 (§8 toll levy power); state Highways Acts | Project sanction order, Detailed Project Report (DPR), forest / environment clearances, land-acquisition awards | | ||
| + | | **2. Toll rules** | NH Fee (Determination of Rates and Collection) Rules, 2008 + 2010, 2013, 2016, 2018 (FASTag), 2024 amendments | Fee notification with vehicle-category rates, annual revision order, base year + WPI escalation calc, local-resident pass clause, return-trip discount clause | | ||
| + | | **3. Concession agreement** | NHAI / state PWD with the concessionaire (BOT-Toll / BOT-Annuity / HAM model) | Concession agreement (full text), signed schedules, performance security, annual fee receipts, traffic-revenue reports, **cost-of-construction | ||
| + | | **4. Daily operations** | Concessionaire / NHAI Toll Operator | Daily collection MIS, plaza-wise vehicle-count by category, FASTag transaction logs, refund register, complaint register | | ||
| + | | **5. Audit / compliance** | CAG, NHAI Internal Audit, MoRTH | CAG audit reports on PPP toll highways, NHAI quarterly review, concessionaire' | ||
| - | [5] Amount | + | → Citizens can ask for any document in this stack under **Section 4(1)(b)(xii) RTI Act** (proactive disclosure |
| - | [6] Name, designation, | + | ===== Real-life: how Ravi Mathur exposed extended toll collection |
| - | [7] Name, designation and office address of the Officers responsible to review and monitor the collection of Toll charges by M/s .............. at above mentioned Toll Naka for closure | + | Ravi Mathur, a 42-year-old textile-trader from Pune, drove the **Mumbai-Pune Expressway** twice a week. The toll for a Class-VII commercial vehicle had quietly risen by 8% in April 2025, but his concern was bigger: local newspapers had reported that the **cost |
| - | I am attaching Application Fee Rs.10/- by way of | + | |
| - | Please send the information to my below address by Registered post. \\ \\ | + | |
| - | Yours faithfully,\\ \\ | + | |
| - | Signature \\ | + | |
| - | Name ……………… \\ | + | |
| - | Address …………… \\ | + | |
| - | Pin Code .........\\ \\ | + | |
| - | Date:.............. | + | |
| - | </WRAP> | + | - The **certified copy of the concession agreement** for Mumbai-Pune Expressway toll operations |
| - | Check Application Format | + | - The **fee notification** as on date with vehicle-category schedule and the WPI base-year + escalation calculation |
| - | For guidance | + | - **Annual toll collection** by year from commissioning to date, with the **certified cost-of-construction figure** |
| - | {(rater>id=1|name=RTI Application for Toll Collection | + | - The **exit-period clause**: date on which toll collection was contractually due to end |
| + | - **Local-resident pass** policy and the **monthly pass** scheme | ||
| + | - **CAG observation** on the project, if any | ||
| + | - **Reasons recorded** for any extension to the original toll period | ||
| + | |||
| + | * **Day 24**: MSRDC replied. Reply confirmed: cost of construction Rs 1,630 crore (1999), accumulated collection by FY 2024-25 = Rs 18,400+ crore. The exit-period clause referenced an **operate-maintain extension till 30 years from concession start**, *not* till cost-recovery as Ravi had assumed. | ||
| + | * **Day 25**: Armed with the actual concession-agreement language, Ravi filed a **representation to the State Road Authority** + a **PIL writ-petition under Article 226** in Bombay HC. The case is in **active hearing**; the records obtained via RTI are part of the petitioner' | ||
| + | * **Day 47**: A **citizen-action public meeting** at Pune got 700+ commuters to sign on. The collected RTI documents made the difference between a " | ||
| + | |||
| + | The decisive lever was **the concession agreement clause on exit period**. Without RTI, Ravi was speculating; | ||
| + | |||
| + | ===== 12 records to demand in your toll-collection RTI ===== | ||
| + | |||
| + | - **Concession agreement**: | ||
| + | - **Project DPR**: detailed project report, design-basis report, **certified cost of construction**, | ||
| + | - **Fee notification + vehicle-category schedule**: current toll rates by category (Car/ | ||
| + | - **Annual fee revision orders**: for each year since commissioning, | ||
| + | - **Annual collection certificate**: | ||
| + | - **Exit-period clause + projected exit date**: the contractual end of toll collection, whether it is fixed-period or revenue-cap, | ||
| + | - **CAG audit observations**: | ||
| + | - **NHAI / state internal-audit reports**: quarterly or annual reviews, with action-points status. | ||
| + | - **FASTag deduction logs**: for a specific vehicle (your own), the deduction history with timestamp, plaza ID, vehicle-category code, and matching transaction ID. (For your own vehicle this is //personal data of yourself//: Section 8(1)(j) does not apply.) | ||
| + | - **Refund register**: date-wise refunds issued for double deduction, wrong-category charging, lane-closure during toll, and reasons recorded. | ||
| + | - **Complaint register**: public complaints received at the plaza, with categorisation, | ||
| + | - **Local-resident exemption policy**: rules under Rule 11(2) of the NH Fee Rules 2008: the 20-km rule for local-resident monthly passes (if applicable to the plaza), with the policy text and the monthly-pass redemption data. | ||
| + | |||
| + | ===== Sample | ||
| + | |||
| + | < | ||
| + | To, | ||
| + | The Public Information Officer, | ||
| + | [NHAI Project Implementation Unit (PIU) / State PWD / MSRDC / etc.], | ||
| + | [Office address], | ||
| + | [PIN Code] | ||
| + | |||
| + | Subject: | ||
| + | 2005: Toll plaza [Toll Naka name / NH or SH number / km], | ||
| + | | ||
| + | |||
| + | Date: [DD MMMM YYYY] | ||
| + | |||
| + | Respected Sir / Madam, | ||
| + | |||
| + | 1. I, [Your full name], aged [age], resident of [house, street, area, | ||
| + | city, PIN], a citizen of India and a regular user of the road in | ||
| + | question, am filing this application under Section 6(1) of the Right | ||
| + | to Information Act, 2005. | ||
| + | |||
| + | 2. Toll plaza details: | ||
| + | Toll Naka No. ........................ (if assigned) | ||
| + | Name of Toll Naka ..................... | ||
| + | Road location (NH/SH + km) ............ | ||
| + | Name of concessionaire / operator ..... | ||
| + | | ||
| + | |||
| + | 3. I respectfully request the following information: | ||
| + | |||
| + | (a) Certified copy of the Concession Agreement between the public | ||
| + | | ||
| + | | ||
| + | (b) Certified copy of the Detailed Project Report (DPR) for the | ||
| + | | ||
| + | | ||
| + | | ||
| + | (c) The current fee notification and vehicle-category schedule : | ||
| + | with rates for Car/ | ||
| + | | ||
| + | pass, monthly pass, and return-trip discount; | ||
| + | (d) For each financial year since commissioning, | ||
| + | | ||
| + | Fee (Determination of Rates and Collection) Rules, 2008 or the | ||
| + | | ||
| + | WPI, and the resulting revision calculation; | ||
| + | (e) For each financial year since commissioning, | ||
| + | | ||
| + | by category, and the local-resident-pass redemption count | ||
| + | | ||
| + | (f) The certified cost-of-construction figure as on financial | ||
| + | | ||
| + | toll collection is contractually scheduled to end, whether | ||
| + | | ||
| + | (g) Any CAG audit observation on the project, with the management | ||
| + | reply and the ATR; | ||
| + | (h) The NHAI / state internal-audit reports for the project for | ||
| + | the last three years; | ||
| + | (i) The FASTag deduction log for vehicle registration number | ||
| + | [your number], for the period | ||
| + | with timestamp, plaza ID, vehicle-category code, transaction | ||
| + | ID, and matching deduction amount; | ||
| + | (j) The refund register entries for the toll plaza named above for | ||
| + | the last three years: including date-wise refunds for double | ||
| + | | ||
| + | (k) The complaint register entries for the toll plaza named above | ||
| + | for the last three years, with categorisation, | ||
| + | and disposal; | ||
| + | (l) The local-resident exemption policy under Rule 11(2) of the | ||
| + | NH Fee Rules, 2008 (or analogous state rule), with the policy | ||
| + | text and the monthly-pass redemption data; | ||
| + | (m) Names, designations, | ||
| + | all Officers responsible for review and monitoring of the toll | ||
| + | | ||
| + | | ||
| + | |||
| + | 4. Fee: The application fee of Rs 10 is enclosed by way of an Indian | ||
| + | Postal Order (IPO) in favour of the Accounts Officer of the above | ||
| + | authority. [If BPL: I am eligible for fee exemption under Section 7(5) | ||
| + | of the RTI Act, 2005: BPL certificate copy enclosed.] | ||
| + | |||
| + | 5. Severability: | ||
| + | sought is exempt under Section 8 of the RTI Act, I request the | ||
| + | remainder be disclosed under Section 10(1) and 10(2) with a reasoned | ||
| + | severance order. | ||
| + | |||
| + | 6. Transfer: Should any part of the subject matter lie outside the | ||
| + | scope of your office, I request transfer under Section 6(3) within | ||
| + | 5 days, with intimation to me. | ||
| + | |||
| + | 7. Section 8 risks pre-empted: | ||
| + | - Section 8(1)(d) " | ||
| + | | ||
| + | | ||
| + | and //RBI v. Jayantilal N. Mistry//, (2016) 5 SCC 136 establish | ||
| + | that procurement / regulatory records do not attract §8(1)(d) | ||
| + | | ||
| + | under §8(1)(d) must specifically identify the part of the | ||
| + | | ||
| + | - Section 8(2) public-interest override: even if a part of the | ||
| + | | ||
| + | | ||
| + | | ||
| + | - Section 8(1)(j) does NOT apply to records of my own FASTag | ||
| + | | ||
| + | | ||
| + | |||
| + | 8. I respectfully request that the information be supplied within | ||
| + | the statutory period of 30 days under Section 7(1) of the Act. In | ||
| + | the event of silence beyond the said period, the non-response will | ||
| + | constitute a deemed refusal under Section 7(2) and I reserve the | ||
| + | right to file a First Appeal under Section 19(1) within 30 days. | ||
| + | |||
| + | Thank you. | ||
| + | |||
| + | Yours faithfully, | ||
| + | |||
| + | |||
| + | ([Your full name]) | ||
| + | |||
| + | Applicant details: | ||
| + | Name: [Your full name] | ||
| + | Address: [Your postal address] | ||
| + | Phone: | ||
| + | Email: | ||
| + | |||
| + | Encl.: (1) Indian Postal Order for Rs 10 / BPL certificate copy; | ||
| + | (2) Self-attested copy of vehicle registration (if FASTag | ||
| + | | ||
| + | </ | ||
| + | |||
| + | → Or skip the manual drafting: **[[https:// | ||
| + | |||
| + | ===== Picking the right PIO: National vs State vs Urban ===== | ||
| + | |||
| + | ^ Toll category ^ Authority ^ PIO target ^ | ||
| + | | **National Highways toll** | **NHAI** under MoRTH | PIO, NHAI Project Implementation Unit (PIU) for that project; Cc Regional Officer / Chief General Manager (CGM) of the NHAI Region | | ||
| + | | **NHAI BOT-Toll concessionaire** | NHAI + concessionaire (private SPV) | Same NHAI PIU as above (NHAI is the public authority; the concessionaire is a contractor). Section 2(f) covers info held by NHAI about the concessionaire. | | ||
| + | | **Expressway toll (state-built)** | State Road Development Corp (e.g., MSRDC for Maharashtra) | PIO, State Road Development Corporation, | ||
| + | | **State Highways toll** | State PWD | PIO, State Public Works Department / State Highways Department | | ||
| + | | **Municipal toll / urban entry tax** | Municipal Corporation | PIO, Municipal Corporation Toll Cell | | ||
| + | | **Border-state entry tax** | State Transport Department | PIO, State Transport Commissioner' | ||
| + | |||
| + | Don't know the PIO? File parallel RTIs to **NHAI PIU + State PWD**: total cost Rs 20: and the responses will name the correct authority. Section 6(3) requires the wrong PIO to **transfer within 5 days**. | ||
| + | |||
| + | ===== 8 common toll grievances and the records that fix them ===== | ||
| + | |||
| + | | ||
| + | - **Wrong vehicle category charged**. Asked to pay LCV rate for a passenger car? Demand the **vehicle-category schedule** + the **CCTV / RFID transaction log** for your transit time. Refunds are routinely processed when the operator' | ||
| + | - **FASTag double deduction**. Same plaza, same vehicle, two debits within 5 minutes. Demand the **transaction log** + **complaint register** entry. NPCI's settlement service auto-reverses on dispute, but RTI surfaces patterns. | ||
| + | - **Local-resident pass denied**. Rule 11(2) of the NH Fee Rules, 2008 mandates a **monthly local-resident pass** (often Rs 150-315) for residents within 20 km of the plaza. Demand the **policy text** + the **list of redemption count** (count alone, not names: privacy-preserving). | ||
| + | - **Toll charged during lane closure or works**. NH Fee Rules require **toll-suspension during works** that close >50% of lanes. Demand the **lane-closure log** + **toll-suspension orders**. | ||
| + | - **Concessionaire' | ||
| + | - **Collection without commissioning certificate**. Some plazas start charging before the road is fully built. Demand the **commissioning certificate** + the **road-completion test report**. | ||
| + | - **No public hearing on fee revision**. Some state rules require notice + hearing. Demand the **revision order** + the **stakeholder-consultation record** if applicable. | ||
| + | |||
| + | ===== After Day 30: the RTI ladder ===== | ||
| + | |||
| + | * **Day 0**: File RTI by Speed Post (AD) to the PIO with copy to senior officer. | ||
| + | * **Day 1-5**: PIO must transfer to right authority within 5 days under §6(3) if necessary. | ||
| + | * **Day 30**: PIO must reply with records or refusal citing a specific Section 8(1) sub-clause + harm test. | ||
| + | * **Day 31**: If no reply → **deemed refusal** under §7(2). File **First Appeal under §19(1)** to the **First Appellate Authority** (typically NHAI Regional Officer | ||
| + | * **Day 31-60**: FAA decides within 30 days (extendable to 45 with reasons). FAA can order **free-of-cost supply** under §7(6). | ||
| + | * **Day 91+**: **Second Appeal under §19(3)** to **CIC** (NHAI is a central public authority) or **State Information Commission** (state PWD / SRDC) within 90 days. Plead **§20 penalty up to Rs 25,000** on the PIO if the refusal was malafide. | ||
| + | * **Parallel routes**: PIL writ-petition under Article 226 is the right route once you have **the documents on record** (Ravi' | ||
| + | |||
| + | → **[[https:// | ||
| + | |||
| + | ===== Pro tips most don't know ===== | ||
| + | |||
| + | * **NH Fee Rules, 2008** is the **single most important document** to read before filing. It governs every NH toll plaza: fees, escalation, local-resident exemption, return-trip discount, plaza spacing (60 km between plazas under Rule 8). Available free at https:// | ||
| + | * **The 60-km rule**: under Rule 8 of the NH Fee Rules 2008, **two toll plazas on the same NH cannot be within 60 km of each other** (with limited exceptions). If you're paying at two plazas within 60 km on the same NH, RTI surfaces the exception order: or the violation. | ||
| + | * **Return-trip discount**: under Rule 11(2A), a one-way return trip within 24 hours qualifies for a **discount** (typically 1.5x the one-way rate, not 2x). Many plazas don't display this. Demand the policy. | ||
| + | * **Monthly local-resident pass**: Rs 315/month for cars in most NH plazas (revisable). Eligibility = Aadhaar + bank receipt showing residence within 20 km. | ||
| + | * **CAG reports** are **already public** at https:// | ||
| + | * **MoRTH parliamentary answers**: Lok Sabha / Rajya Sabha questions on tolls are answered with plaza-wise data. Search at https:// | ||
| + | * **FASTag dispute settlement**: | ||
| + | * **NHAI helpline 1033**: 24×7 toll-free for plaza queries, breakdowns, FASTag failures. | ||
| + | |||
| + | ===== Frequently asked questions ===== | ||
| + | |||
| + | ==== Is the concession agreement a "trade secret" | ||
| + | **No.** The agreement is a **public-authority procurement record** that touches a publicly-collected fee on a public road. Refusal under §8(1)(d) requires (a) demonstrable competitive harm, (b) third-party trade-secret content, (c) no public-interest override under §8(2). The **Eastern Coalfields** (Calcutta HC 2015) and **RBI v. Jayantilal Mistry** (2016) 5 SCC 136 establish the narrow reading. Any §8(1)(d) refusal without harm-test is **appealable** under §19(1). | ||
| + | |||
| + | ==== I want the agreement only: can I get just that, not all 13 items? ==== | ||
| + | **Yes.** Trim the request to the items you need. Shorter RTIs are faster. Item (a): the concession agreement: is the workhorse for most cases. | ||
| + | |||
| + | ==== What's the fee? Can I get a waiver? ==== | ||
| + | **Rs 10** for central authorities (NHAI). | ||
| + | |||
| + | ==== I don't know the PIO of the toll plaza. What do I do? ==== | ||
| + | File parallel RTIs to **NHAI PIU + State PWD + concessionaire' | ||
| + | |||
| + | ==== Can I file an RTI for a private toll operator (concessionaire)? | ||
| + | **Indirectly: | ||
| + | |||
| + | ==== Toll plaza is closed after my construction project. Can I still file? ==== | ||
| + | **Yes.** Records survive the closure of operations: they are required to be retained for 5-10 years under government records-retention rules. Demand the **closure certificate** + final reconciliation. | ||
| + | |||
| + | ==== Can I get a refund for the wrong category charged 6 months ago? ==== | ||
| + | **Yes**: | ||
| + | |||
| + | ==== Can the PIO refuse on Section 11 third-party objection from the concessionaire? | ||
| + | The PIO **must follow §11 procedure**: | ||
| + | |||
| + | ==== I have a state-highway toll grievance: same procedure? ==== | ||
| + | **Yes**, with the PIO target = State PWD or State Roads Development Corporation. Apply state RTI rules for fee + appeal forum (State Information Commission for second appeal). | ||
| + | |||
| + | ==== What's the difference between NH Fee Rules 2008 vs state toll rules? ==== | ||
| + | **NH Fee Rules 2008** govern National Highways exclusively. **State rules** govern state highways and apply different escalation formulas, spacing rules, and local-resident schemes. Always check the state-specific rules before filing on a SH toll. | ||
| + | |||
| + | ==== After I get the records, what's the next step? ==== | ||
| + | Three escalation paths: (a) **CAG / parliamentary committee complaint** if the records show systemic over-collection; | ||
| + | |||
| + | ==== Can I file an RTI in a regional language? ==== | ||
| + | **Yes**: Hindi or any **scheduled language** under the Eighth Schedule. The PIO must respond in the same language or English under §4(4) RTI Act read with state rules. | ||
| + | |||
| + | ===== Citizen-action checklist ===== | ||
| + | |||
| + | - **[ ]** Toll plaza identified: name, NH/SH + km, concessionaire | ||
| + | - **[ ]** Right PIO identified: NHAI PIU vs State PWD vs SRDC vs Municipal | ||
| + | - **[ ]** Items trimmed | ||
| + | - **[ ]** Sample RTI letter customised | ||
| + | - **[ ]** Rs 10 IPO purchased OR BPL certificate attached | ||
| + | - **[ ]** Speed Post (AD) tracking number saved | ||
| + | - **[ ]** 30-day clock set in [[https:// | ||
| + | - **[ ]** First Appeal letter pre-drafted as Day 31 fallback | ||
| + | - **[ ]** CAG report (https:// | ||
| + | - **[ ]** Lok Sabha / Rajya Sabha questions on the plaza pre-checked at https:// | ||
| + | - **[ ]** Disputed FASTag transaction screenshots saved (if applicable) | ||
| + | |||
| + | ===== Related on RTI Wiki ===== | ||
| + | |||
| + | * [[https:// | ||
| + | * [[https:// | ||
| + | * [[: | ||
| + | * [[https:// | ||
| + | * [[https:// | ||
| + | * [[https:// | ||
| + | * [[https:// | ||
| + | * [[:rti-for-pmay-status|RTI for PMAY status: citizen guide]] | ||
| + | * [[: | ||
| + | * [[: | ||
| + | * [[https:// | ||
| + | |||
| + | ===== Sources ===== | ||
| + | |||
| + | * The Right to Information Act, 2005: Sections 4(1)(b)(xii), 4(1)(d), 6(1), 6(3), 7(1), 7(2), 7(5), 7(6), 8(1), 8(2), 10, 11, 19(1), 19(3), 20 | ||
| + | * The Right to Information (Regulation of Fee and Cost) Rules, 2005, Central Government | ||
| + | * The National Highways Act, 1956: §8 toll-levy power | ||
| + | * **National Highways Fee (Determination of Rates and Collection) Rules, 2008** (as amended through 2010, 2013, 2016, 2018 (FASTag), 2024): Rules 5, 8, 11(2), 11(2A) | ||
| + | * Ministry of Road Transport and Highways (MoRTH): concession agreement standard documents (BOT-Toll, BOT-Annuity, | ||
| + | * NHAI: Project Implementation Unit (PIU) directory at https:// | ||
| + | * Comptroller and Auditor General of India: Performance Audit Reports on PPP Toll Highways (https:// | ||
| + | * The Digital Personal Data Protection Act, 2023: Section 44(3) | ||
| + | * //State of UP v. Raj Narain//, (1975) 4 SCC 428: early "right to know" anchor | ||
| + | * //Bhagat Singh v. Chief Information Commissioner//, | ||
| + | * //Eastern Coalfields Ltd. v. WBIC//, Calcutta HC 2015: concession agreements not §8(1)(d) trade secrets | ||
| + | * //RBI v. Jayantilal N. Mistry//, (2016) 5 SCC 136: public-interest override on commercial-confidence claims | ||
| + | * //CBSE v. Aditya Bandopadhyay//, | ||
| + | * NHAI Toll-Free Helpline: **1033** (24×7) for FASTag, plaza issues, breakdowns | ||
| + | |||
| + | {REVIEWED} | ||
| + | |||
| + | //Last reviewed: 4 May 2026: RTI Wiki editorial team. All citations verified against the NH Act 1956, NH Fee Rules 2008 (as amended), MoRTH concession-agreement templates, the RTI Act 2005, and CIC / SC / HC orders as on 4 May 2026.// | ||
| + | |||
| + | {{tag> | ||
| - | ---- | ||
| - | [<>] | ||