Reviewed on 2026-06-20 by Dr. Shrawan Kumar Pathak.
Quick answer. Apply on your state discom's online portal (not the National Power Portal), pick the domestic category, enter your load in kW and upload two documents. By law the discom must release a metered connection within 3 days in metro cities, 7 days in other municipal areas and 15 days in rural areas after a complete application.
This guide is a decision-tree. At each fork you answer one yes or no question, then follow the branch that fits your situation. Start at the top and stop the moment you reach an action that matches where you are stuck.
Electricity supply in India is run by a distribution company, called a discom or power utility, and each state or city has its own. Your bill names it: examples include the various state power corporations, BSES and Tata Power in Delhi, MSEDCL in Maharashtra and so on.
If yes, go to that discom's official website and find the “New Connection”, “New Service Connection” or “Apply Online” tab. If no, check any neighbour's electricity bill, or call the national electricity helpline 1912 from any mobile and ask which discom serves your address. Do not apply on the National Power Portal at npp.gov.in. That is a data dashboard, not a place to apply.
The category decides your tariff and your document list, so choose carefully before you pay.
If the supply is for a house or flat, choose the domestic category, often coded LT-1 or “Low Tension Domestic”. Enter the load you need in kilowatt (kW). A small flat with lights, fans, a fridge and a television usually needs around 2 to 5 kW; add more if you run an air conditioner or a water pump.
A shop or office is a commercial connection, a workshop is industrial, and a borewell or farm pump is agricultural. These have different tariffs and may need extra clearances. If you also run a trade from the premises, sort your municipal trade licence first, because some discoms ask for it as ownership or use proof.
Here is the relief most people do not know. Under the Electricity (Rights of Consumers) Rules, 2020, a connection up to a load of 10 kW needs only two documents: a proof of identity and a proof of ownership or lawful occupancy of the premises.
If you own the premises, use your sale deed, allotment letter, registered agreement, or the latest property tax receipt as ownership proof. If you rent, a registered rent agreement plus a no-objection note from the owner usually works. For identity, Aadhaar, voter ID, passport or driving licence are accepted. A passport-size photograph completes the set.
No. The same Rules say there is no estimation of demand charges for loads up to 150 kW, so the discom cannot stall a normal home or small-business connection on that ground. You will still pay an application fee, a refundable security deposit and any service-line or development charge, but those are quoted after your application is accepted.
Follow these steps on the discom portal in order.
No connection is given without a meter, and by Rule the meter must be a smart prepayment or prepayment meter. If you also want a separate point for an electric vehicle charger, the 2024 amendment lets you apply for a separate EV connection.
Figure: step-by-step flow. If a step stalls, use the grievance or RTI route shown.
This is the fork that protects you. Count the days from when your application was complete, that is, fee paid and documents accepted.
These limits come from the Electricity (Rights of Consumers) Amendment Rules, 2024, which took effect on 22 February 2024 and cut the older 7, 15 and 30 day limits. If the deadline has passed with no connection and no valid reason, you have moved from “applicant” to “aggrieved consumer”, and the next forks are your remedies.
If the reason is fixable, for example a missing document or a load mismatch, correct it and resubmit. If no reason was given, or the reason is unfair, do not keep re-applying. Escalate.
Sometimes the delay is because the service cable must cross a public road or footpath. That is a separate municipal permission, not your job to chase, but it helps to know it exists. See road-cutting permission so you can ask the discom whether this is the hold-up. A genuine delay caused by a builder, as many flat owners face, is covered in our note on a builder delaying your utility connection.
After your application is complete, the discom must release it within 3 days in a metro city, 7 days in other municipal areas and 15 days in rural areas, or 30 days in rural hilly terrain. These are legal maximums set by the 2024 amendment to the Rights of Consumers Rules.
Apply on your own state discom's website under “New Connection” or “New Service Connection”. There is no single all-India application site. The National Power Portal at npp.gov.in is only a data dashboard, so do not apply there.
For a load up to 10 kW you need only two: a proof of identity and a proof of ownership or lawful occupancy, plus a photograph. Discoms cannot demand a long list for an ordinary home connection.
There is an application fee, a refundable security deposit and a service-line or development charge. The exact rupee amounts differ by state, discom and your sanctioned load, so confirm the current figures on your own discom portal before you pay.
No. For loads up to 150 kW there is no estimation of demand charges, so a normal home or small-shop connection cannot be stalled on that ground. You still pay the security deposit and service-line charge after acceptance.
Yes. By Rule no connection is given without a meter, and the meter must be a smart prepayment or prepayment meter. You can also apply for a separate connection just for an electric vehicle charger.
Call 1912 and log a ticket, then file free with the Consumer Grievance Redressal Forum of your discom. If still unresolved, go to the Electricity Ombudsman of your state regulator, which should decide within six months. An RTI to a state-owned discom gets you the inspection report.
Usually yes. A registered rent agreement with a no-objection note from the owner works as occupancy proof in most states. Confirm the exact list on your discom portal, since the accepted occupancy documents vary by state.
Confirm your state discom's fees, category codes and exact document list on its own official portal before you apply, because these figures vary by state and by sanctioned load.