Quick Reply: When an unauthorised structure rises next door and complaints change nothing, RTI to the municipal body's Building Department PIO fetches the three papers that matter: the sanctioned plan, the occupancy or completion certificate status, and the file on your own complaint — notices issued, notings made, action pending. ₹10 starts it, 30 days answers it, and the reply becomes evidence for everything that follows.
Target PIO: the municipal body's building / town planning department
The three asks: sanctioned plan; occupancy or completion status; your complaint's file
Fee: ₹10 — the state schedule
Clock: 30 days, then first appeal in 30, second appeal in 90
Parallel track: writ to the High Court for chronic inaction
Unauthorised construction survives on one thing: nobody putting the municipality's own paper on the table. A sanction file either exists or it does not; an occupancy certificate was either issued or it was not; a complaint was either acted on or parked. Each of those is a record, each record is reachable by RTI, and each reply is signed by an officer. That is why the RTI precedes the courtroom.
To: The Public Information Officer, [Municipal Corporation / Council / Development Authority], [City] Subject: Application under Section 6, RTI Act, 2005 Sir/Madam, kindly provide: 1. A copy of the sanctioned building plan and permission for the property at [full address], permission no. ___ if available, or confirmation that no building permission exists for the structure. 2. The status of the occupancy certificate / completion certificate application for the said property. 3. The file on complaint no. ___ dated ___ regarding unauthorised construction at the said property: inspection notes, the officer deputed, and copies of any notices issued under the municipal building bylaws. 4. The action taken on the notices referred to above, with dates. 5. The name and designation of the officer responsible for building rule enforcement in the ward. Fee of Rs 10 enclosed [IPO / as per the state schedule]. Yours faithfully, [Name, address, phone, email]
Address it to the body that sanctioned or should have sanctioned the work — corporation, council, development authority, or the panchayat for village sites. The wrong address costs two weeks in a Section 6(3) transfer.
Yes — building permissions are public records held by the authority, and third parties obtain them routinely. Personal privacy under Section 8(1)(j) does not cover a building sanction.
Ask for the copy of the sanctioned plan and the permission number. If it exists, the PIO supplies it; if it does not, the PIO says so in writing.
Take the RTI replies — no notice, or unexecuted notice — to the High Court in a writ for enforcement. Chronic inaction with the paper trail attached is exactly what writs are for.
Not by itself. It produces the records that the complaint, the notice-appeal and the writ then act on.
Last reviewed: 26 August 2026. The statutory and judgment anchors were re-verified; an unverifiable 2021 Bombay High Court citation carried by the old page has been removed.