Quick Reply: File RTI to the DRM or RLDA to track Amrit Bharat station redevelopment: DPR, contractor, milestones, expenditure. Rs.10 fee, 30-day reply, full escalation ladder.
Ramesh takes a local train from his town station every morning. For two years he has watched the old platform shed come down, a new roof go up in fits and starts, and a board appear that reads “Amrit Bharat Station”. What he has never seen is a finished station. The contractor changes, the boards change, the deadline changes, and nobody can tell him when it will actually end. So he asks the station master. The station master shrugs. He asks the contractor's clerk. The clerk says “talk to the DRM office”. The DRM office does not reply.
This is the gap a single RTI application closes. Indian Railways is redeveloping more than 1,300 stations right now, and every rupee, every milestone, and every contract detail on those works is a record the public can ask for. This page shows you, step by step, how to get those records from the right office, within the right deadline, and what to do when the reply never comes.
Direct answer. File your RTI to the DRM office of your zonal railway for Amrit Bharat station works. File to RLDA only for the small set of stations handed to the Rail Land Development Authority. Ask for the DPR, contractor name and value, milestones, expenditure, and variation orders. Fee is Rs.10. Reply is due in 30 days.
Most stations being rebuilt today fall under the Amrit Bharat Station Scheme (ABSS). The Ministry of Railways launched it in December 2022. About 1,309 stations were picked under it. Foundation stones for 508 stations were laid on 6 August 2023, and Phase-1 works began on 24 September 2023. ABSS is run zonal-railway-wise — that is, each zonal railway (Northern, Western, Southern, and so on) looks after the stations in its own area. It replaces the older Adarsh Station Scheme that ran from 2009-10.
As of February 2026, 172 stations had been completed under ABSS and 1,165 were still in progress. So if your station is mid-work, you are in the majority.
A smaller track runs in parallel. About 104 stations have been entrusted to RLDA (the Rail Land Development Authority), of which 3 are already commissioned — Rani Kamlapati, Gandhinagar, and Gomtinagar. About 98% of ABSS awards are EPC contracts (that is, the railway pays the contractor to build, not a private partner running the station), while 15 stations are being explored under PPP (public-private partnership, where a private company invests and runs part of the station for a share of revenue).
Why does this split matter for RTI? Because the office you file to depends on which track your station is on.
Door 1 — The DRM office (zonal railway). This is where the vast majority of Amrit Bharat station files live. The CPIO for divisional station works sits inside the DRM's office — usually the Sr. DCM (Senior Divisional Commercial Manager) or the Divisional Engineer. The First Appellate Authority is normally the Addl. DRM (Administration). This routing has been confirmed in CIC decisions such as *Prasanta Basuray v. Ministry of Railways* (CIC/AD/A/2010/000861) and *Chetan Nisar v. Central Railway* (CIC/CRAIL/A/2019/601769), where the Commission treated the DRM's office as the proper divisional PIO for station and redevelopment records.
Door 2 — RLDA. If your station is one of the ~104 entrusted to RLDA, the land and redevelopment files are with RLDA, not the DRM. RLDA has its own CPIO at its headquarters. Check the RLDA website (rlda.indianrailways.gov.in) for the current CPIO name and address.
A quick note on a name you may still see in old news reports: IRSDC (Indian Railway Stations Development Corporation). IRSDC used to run flagship station projects. It was dissolved by the Railway Board on 18 October 2021, and its stations were transferred to the zonal railways. IRSDC no longer exists, its old subdomain does not resolve, and you cannot file an RTI to an office that no longer exists. If an older article or template tells you to write to IRSDC, ignore that — file to the DRM or RLDA instead.
Three things give you the right to ask:
On disclosure limits: Section 8(1)(d) protects the commercial confidence and trade secrets of rival bidders during a tender, and Section 11 requires the railway to give a bidder notice before releasing that bidder's data. But once a contract is awarded, the essentials — the winning bidder, the contract value, and the scope of work — are disclosable under Section 4(1)(b) as part of the public authority's own obligations. In other words, you cannot get a competitor's secret bid, but you can get the name, value, and scope of the bid that won. For a deeper walkthrough of that line, see RTI for tender and contract records and how to ask for tender details.
Pick the ones that match your worry. You do not have to ask all of them.
If you suspect the timeline is slipping, also ask for the scheduled completion date and any time-extension granted, with reasons.
Step 1 — Write the application. There is no fixed form for Central Government authorities. A plain handwritten or typed letter is enough. Put “Application under Section 6 of the RTI Act, 2005” at the top. Name the station, the scheme (Amrit Bharat or RLDA), and list your questions clearly.
Step 2 — Address it. To “The Central Public Information Officer, Office of the Divisional Railway Manager, [Division], [Zonal Railway]” for ABSS works. For RLDA stations, address it to the CPIO, Rail Land Development Authority.
Step 3 — Pay the fee. The fee is Rs.10 for Central Government public authorities, set by the RTI Rules, 2012. Pay by cash against a receipt at the DRM office counter, by Indian Postal Order, by Demand Draft, or online through rtionline.gov.in (the easiest route — no post office trip). BPL applicants are exempt from the fee; attach a copy of your BPL certificate.
Step 4 — Keep proof. Keep the stamped counterfoil, the IPO stub, or the online acknowledgement number. This is your receipt and your evidence later.
Step 5 — Wait 30 days. Under the RTI Act, the authority must reply within 30 days (48 hours where life or liberty is at stake — not the case for station works). If 30 days pass with no reply, or a reply that hides more than it shows, you move to the next step.
RTI works like a staircase. You go up one step at a time.
To: The Central Public Information Officer
Office of the Divisional Railway Manager, [Division], [Zonal Railway]
[For RLDA stations: CPIO, Rail Land Development Authority, New Delhi]
Subject: Application under Section 6 of the RTI Act, 2005 —
Amrit Bharat station redevelopment at [Station name], [State]
Sir/Madam,
Please furnish the following information on record about the
redevelopment of [Station name]:
1. A copy of the sanctioned Detailed Project Report (DPR) and the
approval note.
2. Name of the contractor, contract value, and date of award.
3. The milestone chart and the current physical progress percentage.
4. Total expenditure incurred to date, against the sanctioned cost.
5. All variation orders issued, with reasons for each.
6. Scheduled completion date and any time-extension granted, with reasons.
I am depositing the Rs.10 fee by [cash / IPO / online receipt no. ___].
Sincerely,
[Name], [Address], [Phone]
Last reviewed: 3 July 2026.