You paid for rooftop solar, the panels are on your roof, but the net meter is still not installed and your DISCOM approval is stuck in the queue. Until that meter is in, your subsidy can stall and you cannot export power to the grid. This guide shows you how to track your application, push the DISCOM and your vendor, escalate properly, and protect your subsidy claim.
Reviewed on: 2026-05-29.
Quick answer
A delayed net meter does not mean your rooftop solar is wasted. Find your application ID and acknowledgement, confirm whose stage is pending — your vendor, the DISCOM inspection, or the metering agency — and chase it in writing. Submit a grievance on the DISCOM portal, then escalate to the nodal officer and the state electricity regulator's consumer grievance forum. Keep your vendor invoice and inspection records safe because your subsidy is usually released only after the net meter is commissioned. If your DISCOM is government-owned, an RTI can reveal exactly where your file is stuck.
This guide is for homeowners, housing societies, and small commercial consumers in India who have installed a rooftop solar system and are now waiting on the net-meter installation and DISCOM (distribution company) approval. It is useful if:
Net-metering rules, timelines, fees, and the exact division of work between you, the vendor, and the DISCOM are set by your state electricity regulatory commission and your DISCOM. They vary widely across states. So this guide gives you a method that works everywhere, and tells you where to read the specific rule that applies to you. It does not quote a single national deadline, because there is none.
If your worry is the subsidy money itself rather than the meter, read the companion guide on rooftop solar subsidy not credited or application rejected.
Find your application ID. It is on the acknowledgement your vendor or the portal generated when the net-metering or rooftop-solar application was submitted. Check your email, SMS inbox, and any WhatsApp thread with the vendor. Without the application ID you cannot track or escalate, so make this your first task.
Log in to your DISCOM's online portal or the state solar portal and open your application status. Note the exact stage shown: application received, technical feasibility, inspection scheduled, inspection done, net-meter installation pending, or commissioned. Take a dated screenshot of that status. This single screenshot tells you who to chase.
Pull out your vendor invoice and the work-completion report. Note the date the physical installation was finished. The gap between that date and today is the delay you will be complaining about.
Write down, in one place, the timeline: date you signed with the vendor, date of application, date of any DISCOM inspection, and today. A clear timeline is the backbone of every escalation you will send.
Call your vendor and ask three direct questions. Who is the next stage pending with — the vendor, the DISCOM, or the metering agency? What is the exact reason for the hold? What is the next action and date? Follow the call with an email repeating the same questions, so you have it in writing.
Read your state's net-metering regulations or your DISCOM's solar page to find the published timeline for feasibility, inspection, and meter installation. Match each step against your own dates. Wherever your case has crossed the published time, that is a concrete point you can raise.
Photograph the installed system — panels, inverter, and the meter board — with the date visible. Visual proof that the installation is complete and only the DISCOM meter is missing strengthens your complaint.
Draft your grievance using the template later in this guide. Keep it factual: application ID, dates, the stage that is stuck, and a clear request to install the net meter and approve the connection.
Identify your DISCOM's grievance channel and its nodal officer for rooftop solar or net metering. Most DISCOMs publish a nodal officer and a consumer grievance email on their website. Note the email and any online complaint link.
If a national subsidy is involved, log in to the official national rooftop solar portal and confirm the current status of your subsidy claim and what condition is blocking it. Usually the subsidy waits on the net meter, so keep that record ready for Monday.
| Document | What it proves | Where to get it |
|---|---|---|
| Application ID / acknowledgement (net-metering or rooftop-solar application) | Date you applied; lets you track and escalate | DISCOM portal / state solar portal; email or SMS from vendor |
| Portal status screenshot (dated) | Exact stage your file is stuck at | DISCOM or state solar portal — your application dashboard |
| Vendor invoice and payment receipt | You paid; the commercial relationship and amount | Your installer / vendor |
| Work-completion report / installation certificate | Physical installation is finished; date of completion | Your vendor |
| System photographs (panels, inverter, meter board) | Installation is ready; only the DISCOM net meter is missing | Take dated photos yourself |
| Technical feasibility / sanction approval (if issued) | DISCOM already cleared the connectivity stage | DISCOM portal or letter |
| Inspection report (if inspection done) | Inspection stage is complete; meter installation is the remaining step | DISCOM / inspecting officer |
| Electricity bill / consumer account number | Links your solar application to your existing connection | Latest DISCOM bill |
| Subsidy claim record (if national scheme) | Subsidy is pending and tied to the net meter | Official national rooftop solar portal |
| Vendor and DISCOM correspondence (email / portal tickets) | You followed up; shows who delayed and when | Your email; portal complaint history |
The single most useful thing you can do is identify the exact stuck stage. A rooftop-solar application typically moves through: application submitted, technical feasibility / sanction, physical installation by the vendor, DISCOM inspection, net-meter installation, and commissioning. Open your portal status and find the last completed stage. The next stage is where the delay sits. If the vendor's installation is done but inspection is “pending,” the DISCOM is the bottleneck. If inspection is done but the meter is not fitted, the metering agency or DISCOM stores stage is the bottleneck.
Write your application ID at the top of a single page. Below it, list each date: vendor agreement, application submission, feasibility approval, inspection, and today. This is the timeline you will attach to every complaint. It converts a vague “my solar is stuck” into a specific, dated grievance that an officer cannot brush aside.
Net-metering timelines are fixed by your state electricity regulatory commission, not by a national law. Find your state's net-metering regulations or your DISCOM's rooftop-solar page and note the published number of working days allowed for feasibility, inspection, and meter installation. Where your case has crossed that time, you have a clean point to raise. Do not guess the number — read it from the official source, because it differs by state and is revised from time to time.
If your vendor was empanelled under a government scheme, the vendor has obligations too. Email the vendor asking for the application ID, the current pending stage, the reason, and the next action with a date. Ask the vendor to coordinate with the DISCOM for inspection or meter installation. Keep this email — if the vendor went silent and you paid for a service that was not completed, it becomes evidence in a later consumer complaint.
Use your DISCOM's online complaint system or consumer grievance email. State your application ID, consumer account number, the stuck stage, the dates, and a clear request: complete the inspection and install the net meter, and approve the connection. Attach your status screenshot, invoice, completion report, and photos. Save the complaint or ticket number.
If the first complaint gets no movement, escalate to the rooftop-solar or net-metering nodal officer published on your DISCOM website. Reference your earlier ticket number and the dates. Ask specifically for the meter installation date and the reason for delay in writing. A named officer with a referenced ticket is far harder to ignore.
If you applied for the national rooftop solar subsidy, log in to the official national portal and confirm what condition is blocking your claim. In most cases the subsidy is released after the net meter is installed and the system is commissioned and verified. Keep your application ID, vendor invoice, and inspection record together so that the moment the meter is in, the subsidy claim can move. If the portal shows the claim at risk of lapsing, raise that explicitly in your DISCOM grievance.
If the DISCOM still does not act, every state has a Consumer Grievance Redressal Forum (CGRF) for electricity consumers, and above it an Electricity Ombudsman. These are the proper forums for a DISCOM service failure. Find your forum through your state electricity regulatory commission's website. File your dated timeline and all evidence. This is also the stage where, if your DISCOM is government-owned, an RTI on the file status (see below) gives you ammunition.
| Stage | Action | Forum / Destination | Target timeline |
|---|---|---|---|
| 1 | Ask vendor in writing for application ID, pending stage, and next action | Your empanelled solar vendor / installer | A few working days; keep the email |
| 2 | File a grievance with application ID, dates, and evidence | DISCOM online complaint system / consumer grievance email | As per DISCOM service standards; note ticket number |
| 3 | Escalate to the rooftop-solar / net-metering nodal officer | DISCOM nodal officer (published on DISCOM website) | Reference earlier ticket; ask for meter date in writing |
| 4 | Raise subsidy condition in parallel | Official national rooftop solar portal | Before any subsidy claim window lapses |
| 5 | RTI for file status and recorded reasons (if DISCOM is a public authority) | CPIO / SPIO of your government-owned DISCOM | 30 days (RTI Act) |
| 6 | Formal complaint for service failure | Consumer Grievance Redressal Forum (CGRF), then Electricity Ombudsman of your state | Per your state regulatory commission's rules |
Replace the text in square brackets with your own details before sending.
To, The Nodal Officer (Rooftop Solar / Net Metering) [Name of your DISCOM] [Address of jurisdictional office]
Date: [DD/MM/YYYY]
Subject: Delay in net-meter installation and approval —
Application ID [Your Application ID], Consumer A/c [Your Account No.]
Respected Sir / Madam,
1. I am [Your Name], the registered electricity consumer at
[Service Address], Consumer Account Number [Your Account No.].
2. I applied for a grid-connected rooftop solar net-metering connection
under [scheme name, if any]. My application was submitted on [DD/MM/YYYY] and the Application ID is [Your Application ID] (acknowledgement enclosed — Annexure A).
3. The physical installation of the rooftop solar system was completed
by my empanelled vendor [Vendor Name] on [DD/MM/YYYY], as per the work-completion report and invoice (Annexure B and C). Photographs of the installed system are enclosed (Annexure D).
4. As per the portal status as on [DD/MM/YYYY], my application is pending
at the stage: [exact stage shown, e.g. "inspection done — net meter installation pending"] (screenshot enclosed — Annexure E).
5. The applicable timeline under the net-metering regulations of
[State Electricity Regulatory Commission] for this stage has [crossed / is about to cross], yet the net meter has not been installed and the connection has not been approved.
6. This delay is also holding up my subsidy claim, which is linked to
net-meter installation and commissioning.
7. I therefore request you to:
(a) complete the inspection / net-meter installation and approve the
grid connection at the earliest;
(b) inform me in writing of the reason for the delay and the date by
which the net meter will be installed.
I am available for any inspection or coordination required.
Yours faithfully,
[Your Full Name] Consumer Account No.: [Your Account No.] Application ID: [Your Application ID] [Mobile Number] [Email Address]
Enclosures (Annexure List): A — Net-metering application acknowledgement / Application ID B — Vendor work-completion report C — Vendor invoice and payment receipt D — Photographs of installed system E — Portal status screenshot (dated)
The Right to Information Act, 2005 applies to public authorities. Most state electricity distribution companies are government-owned or substantially state-controlled, which generally makes them public authorities. If your DISCOM is one of these, RTI is a powerful way to break a silent delay. Useful requests include:
An RTI often does what reminders cannot: it forces an officer to put the real status and the reason for delay on the record. To file, see our step-by-step RTI filing guide. The CPIO must respond within 30 days. If you get no reply or an evasive one, use the first appeal under RTI Section 19. For the full appeal sequence, read the first and second appeal guide, and The RTI Playbook covers using RTI in utility and infrastructure disputes.
RTI has clear limits in a net-meter delay:
For a comparable government-portal escalation pattern, see our guide on using CPGRAMS and RTI together.
If your underlying problem is a wrong or inflated bill rather than the meter approval itself, see our guide on a wrong or inflated electricity meter reading. For a new connection or meter at a fresh premises, the method in our new water connection and meter application guide follows the same escalation logic for a different utility.
Responsibility is usually split. Your empanelled vendor installs the solar panels and inverter and files the application. The DISCOM (your electricity distribution company) inspects the installation, approves the connectivity, and either installs the net meter itself or authorises a metering agency to do so. The exact split depends on your state regulator's net-metering rules, so confirm it from your DISCOM's official solar or net-metering page.
Each state electricity regulatory commission sets its own timelines for technical feasibility, inspection, and net-meter installation in the net-metering regulations. There is no single national deadline. Check the timeline published in your state's net-metering regulations or on your DISCOM portal, and count the working days from the date stamped on your application acknowledgement.
It can. Under the national rooftop solar scheme, the subsidy is generally released after the net meter is installed and the installation is commissioned and verified. If the net meter is stuck, the subsidy claim usually cannot be processed. Keep your application ID, vendor invoice, and inspection records ready, and escalate the meter delay so the subsidy timeline is not lost. Confirm the exact subsidy condition on the official national portal.
If your DISCOM is a government-owned or state-controlled distribution company, it is generally a public authority under the RTI Act, 2005, and you can file an RTI with its Central or State Public Information Officer. If your DISCOM is a fully private licensee, RTI may not apply directly; use the electricity regulator's grievance forum and the consumer grievance redressal route instead.
Your strongest proof is the dated application acknowledgement or the application ID generated on the DISCOM or state solar portal, the vendor invoice and work-completion report, photographs of the installed system, and any inspection report or feasibility approval. Save every SMS, email, and portal screenshot with the date visible. These show exactly when you applied and where the file is stuck.
Using your system without an approved net meter and grid connectivity is risky and may breach your DISCOM's connection conditions. Self-consumption rules and safety requirements vary by state and DISCOM. Do not energise a grid-connected system until the DISCOM has approved it. Ask your vendor and DISCOM in writing what is permitted in your case before switching anything on.
Put your follow-up in writing — email and a portal grievance — and ask the vendor for the application ID, current status, and the next step. If the vendor was empanelled under a government scheme, report the non-response to the scheme's grievance channel or the DISCOM nodal officer. If you paid for a service that was not delivered, you also have a consumer-complaint route. Keep the invoice and the contract handy.